ST03: Route 11 (Martinsburg Pike)

Project Purpose

The purpose of the study is to perform value engineering and refinement of the proposed Diverging Diamond Interchange (DDI) at the I-81 Exit 317 interchange with Route 11 to make the project more competitive for SMART SCALE funding. Once the preferred alternative is selected, conceptual design plans will be generated using ground survey. A new engineering cost estimate will be developed that accounts for identified constraints and minimizes contingency costs where possible through evaluation of risks. The study team will investigate opportunities for project phasing.

Survey

No public survey is planned for this study since the improvements have already been identified as part of a previous study effort.

Study Partners

  • Frederick County
  • Winchester/Frederick County Metropolitan Planning Organization

Key Points of Contact

District Lead: Brad Reed

Lead Consultant: Nathan Umberger

Schedule

PHASE DATES TASKS
Phase 1 August 2021 – September 2021 Problem Diagnosis/Brainstorm Alternatives
Phase 2 October 2021 – March 2022 Stakeholder/Public engagement and feedback
Phase 3 March 2022 – July 2022 Investment strategy cost estimation and refinement