ST01: Route 11 (South Main Street)

Project Purpose

The focus of this study is to assess historical crashes on Route 11 (South Main Street) and identify safety improvements. Pleasant Valley Road is Potential for Safety Improvement (PSI) Intersection #13, while the segment between Pleasant Valley Road and Southgate Court is PSI Segment #50. Access management is expected to play a key role in solutions. Multimodal accessibility will be evaluated (very high need for bike access, high need for pedestrian safety improvement) and solutions recommended where appropriate. The study team will investigate opportunities for project phasing.

Survey

The survey regarding potential transportation safety improvements along South Main Street between Pleasant Valley Road and Mosby Road is complete. The survey was provided in English, Spanish and Arabic.

Study Partners

  • City of Harrisonburg
  • Harrisonburg-Rockingham Metropolitan Planning Organization

Key Points of Contact

District Lead: Brad Reed

Lead Consultant: Nathan Umberger

Schedule

PHASE DATES TASKS
Phase 1 August 2021 – September 2021 Problem Diagnosis/Brainstorm Alternatives
Phase 2 October 2021 – March 2022 Stakeholder/Public engagement and feedback
Phase 3 March 2022 – July 2022 Investment strategy cost estimation and refinement