RI02: Route 1 (Chamberlayne Avenue)
Route 197 (W. Laburnum Avenue) to I-95
Project Purpose
The purpose of the project is to improve vehicular safety and multimodal (pedestrian, bicycle, and transit) access and operations. The study corridor along Route 1 (Chamberlayne Avenue) includes multiple segments with vehicular safety concerns as identified by the Potential for Safety Improvement segment rankings (131st, 208th, 221st, etc.).
Survey
The survey regarding potential transportation safety, operations, transit, transit access and bicycle/pedestrian improvements along Chamberlayne Avenue between W. Laburnum Avenue and I-95 is complete.
Study Partners
- City of Richmond
- GRTC Transit System
- Richmond Regional Transportation Planning Organization
Key Points of Contact
District Lead: Liz McAdory
Lead Consultant: Stuart Samberg
Schedule
| PHASE | DATES | TASKS |
|---|---|---|
| Phase 1 | August 2021 – September 2021 | Problem Diagnosis/Brainstorm Alternatives |
| Phase 2 | October 2021 – March 2022 | Stakeholder/Public engagement and feedback |
| Phase 3 | March 2022 – July 2022 | Investment strategy cost estimation and refinement |
Last updated: April 22, 2026