Project Purpose
The purpose of the project is to address the bicycle, pedestrian and vehicular safety concerns, bicycle access needs, and transit and travel demand management needs along the Route 60 study corridor. Two VTrans Priority 2 segments were identified along the study corridor.
Survey
The survey regarding potential transportation safety, operations, transit, transportation demand management and bicycle/pedestrian improvements along Route 60 (Semmes Avenue) between Route 683 (Forest Hill Avenue) and Route 1/301 (Cowardin Avenue) is complete.
Study Partners
- City of Richmond
- GRTC Transit System
- Richmond Regional Transportation Planning Organization
Key Points of Contact
District Lead: Liz McAdory
Lead Consultant: Jeff Kuttesch (RK&K)
Schedule
| PHASE | DATES | TASKS |
|---|---|---|
| Phase 1 | August 2021 – September 2021 | Problem Diagnosis/Brainstorm Alternatives |
| Phase 2 | October 2021 – March 2022 | Stakeholder/Public engagement and feedback |
| Phase 3 | March 2022 – July 2022 | Investment strategy cost estimation and refinement |