LY02: Route 460 Business (Fort Avenue)
Sandusky Drive to Memorial Avenue
Project Purpose
The objectives of the study are to address vehicular and pedestrian safety concerns and to conduct congestion mitigation and capacity preservation along the subject corridor. Five VTrans Priority 1 segments were identified along the study corridor.
Survey
The survey regarding potential transportation safety, congestion, and bicycle/pedestrian improvements along Route 460 Business (Fort Avenue) between Sandusky Drive and Memorial Avenue is complete.
Study Partners
- City of Lynchburg
- Central Virginia Transportation Planning Organization
Key Points of Contact
District Lead: Rick Youngblood
Lead Consultant: Stuart Samberg
Schedule
| PHASE | DATES | TASKS |
|---|---|---|
| Phase 1 | August 2021 – September 2021 | Problem Diagnosis/Brainstorm Alternatives |
| Phase 2 | October 2021 – March 2022 | Stakeholder/Public engagement and feedback |
| Phase 3 | March 2022 – July 2022 | Investment strategy cost estimation and refinement |