N. Combs Road to Cecil Street
The Phase 2 survey regarding potential improvements along the ALT U.S. Route 58 corridor, including the N. Combs Rd. intersection and the segment between N. Combs Rd. and Cecil St. in Lee County is complete.
The purpose of this study is to conduct value engineering of previously developed project recommendations for two locations along the ALT U.S. Route 58 corridor within Lee County. These locations include the N. Combs Road intersection and the segment between N. Combs Road and Cecil Street. This study will focus on improving the project benefits, reducing project cost, and defining project risk. The project recommendations that come from this study will be developed into funding applications for SMART SCALE Round 6 and other transportation funding programs.
District Lead: Blake Ailor and Samantha Farmer
Lead Consultant: Chris Daily
PHASE | DATES | TASKS |
---|---|---|
Phase 1 | May - August 2023 | Diagnose Problems/Brainstorm Alternatives |
Phase 2 | September 2023 – March 2024 | Evaluate Preliminary Alternatives/Conduct Public Outreach and Obtain Feedback/Select Preferred Alternatives |
Phase 3 | March – July 2024 | Conduct Risk Assessment/Develop and Refine Preferred Alternatives/Prepare Cost Estimate and Investment Strategy |
BR-23-10 Phase 1 Executive Summary - PDF, 1.2MB
BR-23-10 Phase 2 Executive Summary - PDF, 1.2MB
BR-23-10 Final Report - PDF, 9MB