ST05: 522/N. Frederick Pike
127/Bloomery Pike TO 699/New Hope Road
Survey
No public survey is planned for this study since lower cost improvements have been identified for this study.
Project Purpose
The focus of this study is to assess the crash history at the unsignalized intersection of Route 522 & Route 127 and identify ways to improve safety. This intersection is ranked #44 on the district Potential for Safety Improvement list, with the majority of crashes occurring on the southbound side of Route 522 where sight distance looking north is limited by the roadway geometry. Solutions identified should be respective of the need to preserve capacity for through travel on Route 522.
Study Partners
- Frederick County
Key Points of Contact
District Lead: Brad Reed
Lead Consultant: Nathan Umberger
Schedule
PHASE | DATES | TASKS |
---|---|---|
Phase 1 | August 2021 – September 2021 | Problem Diagnosis/Brainstorm Alternatives |
Phase 2 | October 2021 – March 2022 | Stakeholder/Public engagement and feedback |
Phase 3 | March 2022 – July 2022 | Investment strategy cost estimation and refinement |