The survey regarding potential transportation safety and bicycle/pedestrian improvements along Route 460 Business (N. Franklin St.) and Route 114 (Peppers Ferry Rd.) is complete.

Project Purpose

The project objectives are to address safety, pedestrian, and bicycle access concerns along the Route 460 Business/N. Franklin Street and  Route 114/Peppers Ferry Road corridors. One node and 2 segments were identified as VTrans Priority 1 needs along the study corridors, with 8 additional segments identified as Priority 2 needs. Goals are to identify safety and operational improvements to improve safety and access for all transportation users.

Study Partners

  • Town of Christiansburg
  • New River Valley Metropolitan Planning Organization

Key Points of Contact

District Lead: Michael Gray

Lead Consultant: Dana Trone

Schedule

PHASE DATES TASKS
Phase 1 August 2021 – September 2021 Problem Diagnosis/Brainstorm Alternatives
Phase 2 October 2021 – March 2022 Stakeholder/Public engagement and feedback
Phase 3 March 2022 – July 2022 Investment strategy cost estimation and refinement

Last updated: May 23, 2024