RI04: Parham Road

RI04 Overview Map

Patterson Avenue TO I-64

Survey

The survey regarding potential transportation safety, operations, congestion mitigation, capacity preservation and bicycle/pedestrian improvements along Route 73 (Parham Rd.) between Patterson Ave. and I-64 is complete.

Project Purpose

The project objectives are to address congestion mitigation and capacity preservation along the Parham Road corridor, along with bicycle and pedestrian safety concerns. Two nodes and 13 segments were identified as VTrans Priority 1 needs along the study corridor, with 10 additional segments identified as Priority 2 needs. Goals are to identify safety and capacity mitigation improvements to improve and preserve the safety and capacity of the corridor for all transportation users.

Study Partners

  • Henrico County
  • GRTC Transit System
  • Richmond Regional Transportation Planning Organization

Key Points of Contact

District Lead: Liz McAdory 

Lead Consultant: Stuart Samberg 

Schedule

PHASE DATES TASKS
Phase 1 August 2021 – September 2021 Problem Diagnosis/Brainstorm Alternatives
Phase 2 October 2021 – March 2022 Stakeholder/Public engagement and feedback
Phase 3 March 2022 – July 2022 Investment strategy cost estimation and refinement

Last updated: May 23, 2024

Alert Icon

Please note that this file is not ADA compliant. Choose one of below options: