Route 17 Business (Main Street) TO Route 1420 (Hillside Drive)
The survey regarding potential transportation safety, operations, access and bicycle/pedestrian improvements along Route 17 between Route 17 BUS (Main St.) and Route 1420 (Hillside Dr.) in Gloucester is complete.
Goal: Develop project ideas focused on VTrans Priority 1 needs for SMART SCALE round 5. Focus on access management, capacity preservation, bicycle/pedestrian access, and transit access.
District Lead: Stephen Haynes
Lead Consultant: Chris Daily
PHASE | DATES | TASKS |
---|---|---|
Phase 1 | August 2021 – September 2021 | Problem Diagnosis/Brainstorm Alternatives |
Phase 2 | October 2021 – March 2022 | Stakeholder/Public engagement and feedback |
Phase 3 | March 2022 – July 2022 | Investment strategy cost estimation and refinement |